Pkg 1: Primary
Collection, Secondary Transport and Drain Cleaning
- Tender call for Demonstrative Phase on April 11, 2008 (First Call) and then on May 2, 2008 (Second Call)
-
Selection of Successful Bidder for
Demonstrative Phase Tender – M/s Sheetal Group of Companies in
May 2008.
- Tender call for Main
Phase on Dec 16, 2008
- Selection of Successful
Bidder for Main Phase Tender – M/s Sintex Industries Ltd. in
March 2009.
- Tender call for Package
1B: Secondary
Collection Points on Jan 30, 2010
- Selection of Successful
Bidder for Package 1B Tender – M/s P. S. Industries Ltd. in
April 2010
Pkg 2: Transfer Station
and Compost Plants
- Notice Inviting
Pre-Qualification for Pkg 2 -September 12,2008
- Submissions of Completed
Applications for Pre-Qualification for Pkg 2 - October
24,2008
- Completion of the
Pre-Qualification Process for Pkg 2 after concurrence on the
same from JICA – April 22, 2009
- Issue of Tender Documents
to Pre-Qualified Bidders - April 27, 2009
- Close of Tender for
Pkg 2 – June 26, 2009
- Completion of the
Technical Evaluation for Pkg 2 after concurrence on the same
from JICA – Nov 21, 2009
- Financial Bid Opening in
presence of Technically Qualified Bidders – Nov 27, 2009
- Completion of the
Financial Evaluation for Pkg 2 after concurrence on the same
from JICA – Feb 28, 2010
- The Contract concluded
with the Selected Bidder – M/s Jamshedpur Utilities & Services
Company Limited (JUSCO) in March 2010.
Pkg 3: Regional Waste
Management Center
- Notice Inviting
Pre-Qualification for Pkg 3 on September 12,2008
- Submissions of Completed
Applications for Pre-Qualification for Pkg 3 - October
24,2008
- Completion of the
Pre-Qualification Process for Pkg 3 after concurrence on the
same from JICA – April 22, 2009
- Issue of Tender
Documents to Pre-Qualified Bidders – May 04, 2009
- Close of Tender for
Pkg 3 – July 31, 2009
- Submission of Technical
Evaluation Report for Pkg 3 to JICA – Sep 24, 2009
- Request from JICA for
Re-tendering for Pkg 3 – Nov 24, 2009
- Bidding Documents with
Must Conditions for Pkg 3 finalised after concurrence on the
same from JICA and NIT published on 31st March 2010
- Close of Tender for Pkg 3 – May 31, 2010
- Publication of the result of Part-I “Must
Condition” Evaluation – June 02, 2010
- Completion of the Technical Evaluation for
Pkg 3 after concurrence on the same from JICA – July 28, 2010
- Financial Bid Opening in presence of
Technically Qualified Bidders – August 02, 2010
- Completion of the Financial Evaluation for
Pkg 3 after concurrence on the same from JICA – August 12, 2010
- Contract concluded with the Selected
Bidder – M/s SMS Infrastructure Limited (SMS) in September 2010. |